Intending to obtain the SAP E_ACTCLD_23 certification is an excellent step for a project manager looking to advance in their career. SAP Certified Specialist - SAP Activate for Cloud Solutions Project Manager certification exam is beneficial for individuals who are looking to demonstrate their expertise in SAP Activate projects. With the certification, a candidate can show that they possess the skills and knowledge to manage projects independently, thus increasing their job opportunities and earning potential. SAP Certified Specialist - SAP Activate for Cloud Solutions Project Manager certification also assures employers that the candidate has standardized project management principles and can manage an SAP Activate cloud-based project efficiently.
NEW QUESTION # 55
In which phase do you run the user acceptance test?
- A. Realize
- B. Build and Test
- C. Final Preparation
- D. Deploy
Answer: A
NEW QUESTION # 56
What is a difference between the SAP Activate methodology for a new implementation of SAP S/4HANA cloud edition and a new implementation of SAP S/4HANA on-premise?
- A. For on-premise, there is an additional Q-Gate for system installation
- B. For the cloud edition, there is an additional Q-Gate for integration with on-premise systems
- C. For on-premise, there are additional deliverables for the system setup
- D. For the cloud edition, there is an additional work stream for integration with on-premise systems
Answer: C
NEW QUESTION # 57
What information doest the project team need before they can correctly estimate the relative size of backlog user stories?
- A. test strategy
- B. overall project schedule
- C. available project resource
- D. definition of Done
Answer: D
NEW QUESTION # 58
What is the difference between the "new implementation of SAP S/4HANA Cloud" And the "new implementation of SAP S/4HANA transition path? There are 2 answers to this question.
- A. Upgrade of SAP S/4HANA cloud are managed by SAP, and upgrades of SAP S/4HANA are managed by the customer
- B. Different sets of workstreams are used for these transition paths
- C. SAP S/4HANA uses the implementation guide (IMG) and the in-app extensibility option for Configuration and development, and SAP S/4HANA Cloud uses SSCUs and the side- by-side Extensibility option
- D. There are different roles in the application design and configuration workstream
Answer: A,C
NEW QUESTION # 59
Which of the following is a key characteristic of the Agile project approach?
- A. Formal and detailed documentation
- B. Frequent and detailed project scheduling
- C. Iterative build with frequent inspections
- D. Frequent quality gates
Answer: C
NEW QUESTION # 60
What structure level do you see when you access the Roadmap Viewer and chose work stream navigation?
Please choose the correct answer.
- A. Task
- B. Deliverable
- C. Scenario
- D. Scope Item
Answer: B
NEW QUESTION # 61
Which of the following scenarios are enabled for the "selective data transition" Transition Path with the SAP landscape transformation tool? There are 3 answers to this question.
- A. Security migration
- B. Extraction of business units
- C. System consolidation
- D. System upgrade
- E. Consolidation through online data replication
Answer: B,C,E
NEW QUESTION # 62
Which of the following is part of the Explore phase in the "New implementation od SAP S/4 HANA Cloud" transition path?
- A. Setup and enablement
- B. Solution validation and Delta design
- C. Fit-to-standard
- D. Simplification and custom code impact analysis
Answer: C
NEW QUESTION # 63
How can a customer get access to SAP Cloud ALM?
- A. SAP Cloud ALM fair usage rights are included in SAP MayAttention and SAP ActiveAttention at NO additional cost
- B. SAP Cloud ALM fair usage rights are included in SAP Preferred Success and SAP Preferred Care at NO additional cost
- C. SAP Cloud ALM fair usage rights are included in SAP Enterprise Support, cloud editions at NO additional cost
- D. SAP Cloud ALM can be bought on the SAP Store
Answer: C
NEW QUESTION # 64
What is Scrum of Scrums?
- A. Frequent inspection of code and configuration prior to quality gates
- B. Integration meeting among the various Scrum teams
- C. Alternative to regular Scrum process for smaller teams
- D. Mechanism for gathering and validating requirements
Answer: B
NEW QUESTION # 65
In which phase of the SAP Activate methodology does the team complete the Cut-over Rehearsal? Please choose the answer.
- A. Prepare
- B. Deploy
- C. Explore
- D. Realize
Answer: B
NEW QUESTION # 66
In SAP Activate, what tool is used in the agile delivery approach during the Realize phase to make forecasts based on actual data?
- A. Burndown chart
- B. Release plan
- C. Project plan
- D. Product increment
Answer: A
NEW QUESTION # 67
What are some core objectives of business process monitoring? 2 correct answers
- A. to provide reverse business process analysis
- B. to increase business process execution quality
- C. to provide process update and change feedback
- D. to provide transparency over end-to-end processes
Answer: B,D
NEW QUESTION # 68
What are some of the key topics covered in the Customer Team Enablement workstream? Note: There are 3 correct answers to this question.
- A. Planning skills
- B. Project management
- C. Technical expertise
- D. Project sourcing approach
- E. Solution expertise
Answer: B,C,E
NEW QUESTION # 69
Which new project roles are introduced with the SAP Activate Agile methodology? There are 2 answers to this question.
- A. Integration Lead
- B. Design Thinking Coach
- C. Product Owner
- D. SCRUM Master
Answer: C,D
NEW QUESTION # 70
What are some activities the project team will perform in executing project work during the Explore Phase?
- A. Collect project data and report on progress and performance
- B. Manage risks and implement risk response activities
- C. Deal with user authorization requests
- D. Manage Background Jobs, Input and Output
- E. Establish and manage internal and external communications
Answer: A,B,E
NEW QUESTION # 71
What is the correct order of the SAP Activate Methodology phases?
- A. Prepare -> Discover -> Explore -> Realize -> Deploy -> Run
- B. Discover -> Prepare -> Explore -> Realize -> Deploy -> Run
- C. Plan -> Build -> Run -> Sustain
- D. Plan -> Design -> Build -> Operate
Answer: B
NEW QUESTION # 72
Which of the following is not a Phase in the SAP Activate Methodology?
- A. Prepare
- B. Discover
- C. Go-Live & Support
- D. Explore
- E. Realize
- F. Deploy
Answer: C
NEW QUESTION # 73
Which of the following is part of the Explore phase in the "New Implementation of SAP S/4HANA Cloud" transition path?
- A. Setup and enablement
- B. Fit-to-standard
- C. Solution validation and Delta design
- D. Simplification and custom code impact analysis
Answer: C
NEW QUESTION # 74
......
SAP E_ACTCLD_23 certification exam is an essential certification for individuals who work as project managers in cloud solution environments. It is a globally recognized certification that demonstrates the candidate's expertise and knowledge in SAP Activate methodology and their ability to apply it to cloud solution projects. E_ACTCLD_23 exam covers a range of topics and is designed to assess the candidate's ability to manage and oversee the implementation of SAP Activate methodology in cloud solutions projects.
Full E_ACTCLD_23 Practice Test and 170 Unique Questions, Get it Now!: https://www.vce4dumps.com/E_ACTCLD_23-valid-torrent.html
Best Value Available Preparation Guide for E_ACTCLD_23 Exam: https://drive.google.com/open?id=1ZfjvSg75zHpJJH18ytdqbjBTDOg8sZxx