NEW QUESTION 20
Which is a transformational flow process?
- A. Reviewing Benefits
- B. Benefits Profiling
- C. Benefits Management
- D. Realizing the Benefits
Answer: D
NEW QUESTION 21
Which role focuses on monitoring the progress of the programme at a strategic level?
- A. Senior responsible owner
- B. Programme manager
- C. Risk manager
- D. Sponsoring group
Answer: B
NEW QUESTION 22
Which is MOST LIKELY to trigger premature closure of a programme?
- A. The scope of one of the key projects has been changed
- B. The last tranche has been completed as per the programme plan
- C. The programme is no longer aligned with corporate strategy
- D. There is a change of senior responsible owner
Answer: C
NEW QUESTION 23
Why does a programme require a continual process of realignment?
- A. The programme plan describes the activities required to implement its projects
- B. Programmes need to be able to respond to changes in corporate strategy
- C. An organization's projects should belong to a single programme
- D. Programmes deal with outcomes whereas projects deal with outputs
Answer: A
NEW QUESTION 24
Which of the following statements about the business change manager role are true?
1. It provides a bridge between the programme and business operations
2. It delivers the new capability to business operations
- A. Only 2 is true
- B. Both 1 and 2 are true
- C. Neither 1 or 2 is true
- D. Only 1 is true
Answer: D
NEW QUESTION 25
What programme role is MOST likely to also have a role within a project board to represent the interests of the business?
- A. Programme Board
- B. Programme Manager
- C. Business Change Manager
- D. Programme Office
Answer: A
NEW QUESTION 26
Which of the following statements about the core elements of successful communications is true?
1. Stakeholder analysis is required
2. Audit trail is established
- A. Only 2 is true
- B. Both 1 and 2 are true
- C. Neither 1 or 2 is true
- D. Only 1 is true
Answer: D
NEW QUESTION 27
Which is a characteristic of a programme?
- A. It co-ordinates, directs and oversees the implementation of a set of related projects and activities
- B. It defines an organization's approach to achieving its corporate objectives in a given area of business
- C. It manages the planning, monitoring and control of projects
- D. It delivers one or more outputs in accordance with an agreed business case
Answer: A
NEW QUESTION 28
What term represents the desired state of the organization achieved after transition?
- A. Output
- B. Benefit
- C. Outcome
- D. Capability
Answer: C
NEW QUESTION 29
What document provides terms of reference for the Sponsoring Group?
- A. Resource Management Plan
- B. Programme Brief
- C. Organization Structure
- D. Quality and Assurance Strategy
Answer: C
NEW QUESTION 30
Which occurs in identifying a Programme?
- A. Confirmation of the Programme Mandate to trigger the start of the programme
- B. Consolidation of the outputs from identifying a Programme in the Programme Definition Document
- C. Appointment of the Business Change Team to prepare the Programme Mandate
- D. Creation of the Stakeholder Engagement Strategy to support consultation on the Programme Brief
Answer: A
NEW QUESTION 31
Which area of management within programme quality tracks and protects project outputs?
- A. Asset
- B. Process
- C. Information
- D. Supply chain
Answer: A
NEW QUESTION 32
Which response pays a third party to accept a risk?
- A. Avoid
- B. Prepare contingent plans
- C. Accept
- D. Transfer
Answer: D
NEW QUESTION 33
Which document should be used to provide guidance on the standards that should be followed when producing outputs?
- A. Project Brief
- B. Programme Brief
- C. Programme Blueprint
- D. Projects Dossier
Answer: A
NEW QUESTION 34
Which is the BEST description of the purpose of the Projects Dossier?
- A. Describes the context when starting up projects
- B. Provides detailed requirements for each project
- C. Specifies a thorough brief for starting each project
- D. Lists the projects involved in the delivery of the Blueprint
Answer: D
Explanation:
Projects dossier provides a list of projects required to deliver the blueprint, with high-level information and estimates.
NEW QUESTION 35
Which is a feature of an effective programme organization?
- A. A quality assured configuration management system
- B. Clear accountability for each management role
- C. A business case agreed by the stakeholders
- D. Monitored and controlled programme changes
Answer: D
NEW QUESTION 36
What role has a focus on designing benefit measures within a programme to track business performance against targets?
- A. Senior Responsible Owner
- B. Programme Manager
- C. Benefits Realization Manager
- D. Business Change Manager
Answer: C
NEW QUESTION 37
In which perspective are risks MOST likely to be found if a transition is not properly managed and resourced?
- A. Programme
- B. Operational
- C. Strategic
- D. Project
Answer: B
NEW QUESTION 38
......
Reliable MSP Programme Management Certifications MSP-Foundation Dumps PDF Mar 08, 2022 Recently Updated Questions: https://www.vce4dumps.com/MSP-Foundation-valid-torrent.html
Latest MSP-Foundation Exam Dumps for Pass Guaranteed: https://drive.google.com/open?id=1c1b_F1V656PAo_Twm8OK0pVypM6gmwhe