NEW QUESTION 118
Which is shown in a product breakdown structure?

  • A. What resources are required to develop the products
  • B. Management stages, major products and control points
  • C. The major products that are to be developed in a plan
  • D. In which order the products should be created

Answer: C

Explanation:
Section: Volume B

 

NEW QUESTION 119
Which is a responsibility of a Team Manager?

  • A. Ensuring delivery of products in the Managing Product Delivery process
  • B. Setting Work Package tolerances
  • C. Producing Highlight Reports for the Project Manager
  • D. Reviewing the status of the stage

Answer: A

 

NEW QUESTION 120
How does the 'managing product delivery' process achieve its purpose?

  • A. By escalating issues and risks that cannot be resolved within stage tolerance
  • B. By agreeing requirements for how project work should be undertaken
  • C. By producing highlight reports to enable the project board to oversee the work
  • D. By requiring the project manager to produce and monitor team plans

Answer: B

 

NEW QUESTION 121
Which step in the issue and change control procedure considers alternative options for responding to an issue that is being managed formally?

  • A. Examine
  • B. Propose
  • C. Decide
  • D. Capture

Answer: B

 

NEW QUESTION 122
What must be included in the risk management approach, as a minimum requirement for applying the risk theme?

  • A. Estimations of the likelihood and impact of risks
  • B. A description of the risk management procedure
  • C. An explanation of the company's risk appetite
  • D. The names of the assigned actionees for each risk

Answer: B

Explanation:
Explanation
Reference https://www.prince2primer.com/prince2-2017-risk-theme-changes/

 

NEW QUESTION 123
During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?

  • A. End Stage Report
  • B. Team Plan
  • C. Project Plan
  • D. Work Package

Answer: C

 

NEW QUESTION 124
Which is an objective of the 'directing a project' process?

  • A. To define how risks, issues and changes will be managed
  • B. To review and approve a project mandate
  • C. To ensure corporate or programme management has an interface to the project
  • D. To obtain approval for completed products

Answer: C

Explanation:
Explanation
Reference http://prince2.wiki/Directing_a_Project#Objective

 

NEW QUESTION 125
Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?

  • A. Corporate group
  • B. Project Assurance
  • C. Executive
  • D. Project Board

Answer: A

 

NEW QUESTION 126
Identify the missing word in the following sentence, A purpose of the [?] theme is to control any unacceptable deviations from the project's objectives.

  • A. Risk
  • B. Plans
  • C. Progress
  • D. Change

Answer: C

 

NEW QUESTION 127
Why is a project brief produced?

  • A. To record the how the project will communicate with its stakeholders
  • B. To provide a full and firm foundation for the initiation of a project
  • C. To act as a trigger for the 'starting up a project' process
  • D. To be used by the project board as a basis for reviewing the progress of a project

Answer: B

 

NEW QUESTION 128
A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?

  • A. Write an Exception Report
  • B. Raise an off-specification
  • C. Raise a request for change
  • D. Amend the Work Package

Answer: B

 

NEW QUESTION 129
Which is a task of product-based planning?

  • A. Create the product flow diagram
  • B. Prepare the schedule
  • C. Design the plan
  • D. Analyze the risks

Answer: A

 

NEW QUESTION 130
Which is a responsibility of the project board?

  • A. To ensure production of the project's outputs
  • B. To implement the change control approach
  • C. To manage the team managers and project support
  • D. To ensure effective communication with external stakeholders

Answer: D

Explanation:
Reference: http://prince2.wiki/Organization#Project_Board

 

NEW QUESTION 131
According to PRINCE2, why might there be more than one business case for a project?

  • A. The project may be in a programme environment
  • B. There may be more than one work package being delivered in the project
  • C. The project may be in a commercial environment with a number of suppliers
  • D. There may be more than one management stage in the project

Answer: C

Explanation:
Section: Volume B
Explanation/Reference:
Reference https://www.prince2primer.com/prince2-practitioner-questions-answers-business-case/

 

NEW QUESTION 132
Which role is responsible for creating Checkpoint Reports?

  • A. Team Manager
  • B. Senior Supplier
  • C. Project Support
  • D. Change Authority

Answer: A

 

NEW QUESTION 133
Which is a purpose of the Quality theme?

  • A. Establish how the project will ensure that all products created meet their requirements
  • B. Identify all the products of the project to ensure the scope has been adequately defined
  • C. Determine the communication needs of the organization's quality assurance function
  • D. Establish quality assurance to maintain the quality management system

Answer: A

Explanation:
Section: Volume B

 

NEW QUESTION 134
A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?

  • A. Write an Exception Report
  • B. Raise an off-specification
  • C. Raise a request for change
  • D. Amend the Work Package

Answer: B

Explanation:
Section: Volume A

 

NEW QUESTION 135
Which product summarizes progress and is used to decide whether to amend the project scope or stop the project?

  • A. Checkpoint Report
  • B. Product Status Account
  • C. End Project Report
  • D. End Stage Report

Answer: D

 

NEW QUESTION 136
Identify the missing words in the following sentence. A project is [ ? ] organization that is created for the purpose of delivering business products.

  • A. a technical
  • B. a corporate
  • C. an external
  • D. a temporary

Answer: D

 

NEW QUESTION 137
Identify the missing words in the following sentence. The purpose of the Starting up a Project process is as much about [?] as it is about requesting authorization to initiate viable projects,

  • A. obtaining approval from all stakeholders
  • B. producing an achievable Project Plan
  • C. setting up the required project controls
  • D. preventing poorly-conceived projects from ever being initiated

Answer: D

 

NEW QUESTION 138
Which describes the 'Identify Risks' step within the recommended risk management procedure?

  • A. Gather information about the project environment and objectives
  • B. Identify responses to risks documented in the Business Case
  • C. Identify uncertainties that may impact on the delivery of the project objectives
  • D. Identify the roles to be involved in risk management activities

Answer: C

 

NEW QUESTION 139
What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?

  • A. Controlling a Stage
  • B. Managing a Stage Boundary
  • C. Directing a Project
  • D. Starting up a Project

Answer: A

 

NEW QUESTION 140
What is a benefits management approach used to assess?

  • A. The suitability of the project management team structure
  • B. The effectiveness of the project strategies
  • C. How the project has progressed against its plans
  • D. How the project's products have performed when in operational use

Answer: D

Explanation:
Section: Volume B
Explanation/Reference: https://mplaza.pm/prince2-benefits-management-approach-template/

 

NEW QUESTION 141
......

Get 100% Passing Success With True PRINCE2Foundation Exam: https://www.vce4dumps.com/PRINCE2Foundation-valid-torrent.html

Premium Quality PRINCE2 PRINCE2Foundation Online dumps: https://drive.google.com/open?id=1LNbZPJPBOC-igcnkVL_OW_7cKTUPCbH-