Do you want to enter into the big international companies? Do you want to meet influential people and extraordinary people of IT field? Do you want to make some achievements in your career? Getting the Construction-Manager certification may be the first step for you. As the major exam of CMAA, CMAA are recognized by most companies and it proves your IT ability. But the problem is how to get CMAA certification quickly. It will be twice as much as can be accomplished with half of effort with a good helper. VCE4Dumps will be a good helper in the course of preparing your Construction-Manager test dumps. You just need to spend your spare time to practice the Construction-Manager vce files and Construction-Manager test dumps, the test wll be easy for you.
The service of VCE4Dumps
First, you can download the trial of Construction-Manager free vce before you buy.
Second, you will be allowed to free updating the Construction-Manager exam dumps vce one-year after you become a member of us.
Third, we offer 24/7 customer assisting to support if you have any problems about the downloading or purchasing the Construction-Manager vce dumps.
Forth, we adhere to the principle of No help, Full refund. The money will be full refund if you got a bad result with our Construction-Manager test dumps.
Why you choose VCE4Dumps
First, it is professional. Construction-Manager exam dumps vce and Construction-Manager dumps pdf are created by our IT workers who are specialized in the study of real Construction-Manager test dumps for many years and they check the updating of Construction-Manager vce dumps everyday to make sure the valid of Construction-Manager dumps latest, so you can rest assure of the accuracy of our Construction-Manager vce dumps. The Construction-Manager vce files of our VCE4Dumps contain questions and correct answers and detailed answer explanations and analysis, which apply to any level of candidates. You will pass the test with high rate If you practice the Construction-Manager dumps latest seriously and skillfully.
Second, the pass rate is high. May be you are still wonder how to choose, we can show you the date of our pass rate in recent years. The Construction-Manager exam dumps vce helped more than 100000+ candidates to get the certification and the pass rate is up to 79%. Many customers of VCE4Dumps reflected that our Construction-Manager vce dumps have 80% similarity to the real Construction-Manager test dumps. So if you prepare the Construction-Manager dumps pdf and Construction-Manager dumps latest seriously and remember the key points of Construction-Manager test dumps, your pass rate will reach to 80%. So you need to pay much attention to the Construction-Manager exam dumps vce before test.
Third, it is convenient. Online test engine is only service you can enjoy from our website. It is a simulation of formal test and you can feel the atmosphere of real test. What's more, it allows you to practice the Construction-Manager dumps pdf in any electronic equipments. If you open it with internet, you can do the Construction-Manager vce files anywhere. When you are waiting people or taking a bus, you can remember or practice the Construction-Manager vce files without any limitation.
CMAA Construction-Manager Exam Syllabus Topics:
| Section | Objectives |
|---|---|
| Project Controls and Risk Management | - Risk identification and mitigation - Project performance monitoring |
| Contract Administration | - Change orders and claims management - Construction contracts and procurement |
| Schedule Management | - Critical path method (CPM) - Schedule development and tracking |
| Quality and Safety Management | - Quality assurance and quality control - Construction safety programs and compliance |
| Cost and Financial Management | - Cost estimating and control - Cash flow and financial reporting |
| Project Closeout and Commissioning | - Commissioning and handover - Closeout procedures and documentation |
| Project Management Fundamentals | - Project planning and delivery methods - Scope, schedule, and budget management |
CMAA Certified Construction Manager (CCM) Sample Questions:
1. A program management function that promotes the efficient use of completed projects and/or parts of completed projects to maximize the owner's return on investment is called
A) project financing.
B) contract packaging.
C) project phasing.
D) resource-leveling.
2. Which of the following statements BEST describes the recommended approach CMs should take with respect to building information modeling (BIM)?
A) The CM should not recommend the use of BIM.
B) The CM should assure the owner has considered using BIM.
C) The CM should not discuss BIM unless requested by the owner.
D) The CM should require the owner to use BIM.
3. Which of the following would MOST likely help provide benchmarking for a sustainable project?
A) Department of Transportation
B) Housing and Urban Development
C) Energy Star program
D) Environmental Protection Agency
4. A dispute arises during construction after the contractor encounters what they feel is unsuitable material. The CM is not notified about the areas of concern, and the contractor hauls 10.000 cy of material offsite. Three months later, the contractor submits a claim for additional cost to haul the material off. The CM should advise the owner that
A) the claim is not valid because the contractor failed to provide timely notice.
B) the owner should pay for the haul.
C) the owner should pay 50% of the haul since the contractor did not notify the CM first.
D) the owner should pay the claim due to lack of owner information.
5. It is ideal for the CM to assist in mitigating potential impacts and unforeseen issues that may develop as early as the
A) design phase.
B) construction phase.
C) pre-design phase.
D) post-construction phase.
Solutions:
| Question # 1 Answer: C | Question # 2 Answer: B | Question # 3 Answer: C | Question # 4 Answer: A | Question # 5 Answer: C |